Please note the following re-surfacing works will be taking place for approximately 2 weeks commencing 29/10/2018. The road will remain accessible until 6th November when it will be closed as per the schedule below.

- The resurfacing and associated works will take place from the junction with Cavendish Road to Tangley
- Works are due to start 29/10/2018 and are set to last two weeks concluding on 09/11/2018
- Works are being carried out by Iain Marshal Surfacing
- 29/10/2018 – signage will be set up as required. Start works installing granite sets around storm water gullies – Road open as normal
- 30/10/2018 – continue installing granite sets around storm water gullies – Road open as normal
- 31/10/2018 – relay existing granite sets in several places – Road open as normal
- 01/11/2018 – raise all iron works to appropriate levels – Road open as normal
- 02/11/208 – break out necessary areas and lay base coat tarmac accordingly – Road open as normal
- 05/11/2018 – plane off existing surface half road at a time – Road open as normal – take extra care when passing through works
- 06/11/2018 – lay new surface – Road closed from 08:00 until 16:00 – Access for local residents via pedestrian access. Diversion signs will be installed as required
- 07/11/2018 – lay new surface and reinstate road markings – Road closed from 08:00 until 16:00 – Access for local residents via pedestrian access. Diversion signs will be installed as required
If you require any further information please call Paul Scott on 07880 707 989 or email paulscott@stgeorgesra.com